Projects:
Solar Farms

We have graded more than 2,500 acres for solar farm development since June 2021. Upon completion, these farms will provide power to an estimated 91,000 homes annually.

Project Details

Wood County Solar Project

Project Area:

1,200 Acres

Power Output:

150 Megawatts (MW)

Estimated Homes Powered:

40,000

Location:

Wood County, Wisconsin

Owner:

Wisconsin Power & Light

Project Status:

Completed November 2022

Project Website:

The Wood County Solar Project is a 150-megawatt (MW) solar project located in Wood County, Wisconsin in the Town of Saratoga. The Wood County Solar Project connects into the electrical transmission grid directly through the local substation. The project positively impacts the environment and generates enough clean, low-cost energy to power tens of thousands of homes.
Mashuda Contractors' Work:
  • 1.2 Million CY of Excavation Completed
  • 8.8 Miles of Access Roads Built
  • 35 Acres of Gravel Laydown Areas Installed
  • Grading Activities Completed in 4 Months (June 27th, 2021 to October 25th, 2021)
Project Details:
    • 388,350 Solar Panels Installed
    • 74,127 Steel Piles Installed
    • 41 Inverters Installed
    • 819 Miles of Cable Installed
    Click on an image below to open the Wood County Solar Project Photo Gallery.
    Back to Home Page→

    Project Details

    Cassville Solar Project

    Project Area:

    325 Acres

    Power Output:

    50 Megawatts (MW)

    Estimated Homes Powered:

    13,000

    Location:

    Cassville, Wisconsin

    Owner:

    Wisconsin Power & Light

    Project Status:

    Expected Completion Q4 2023

    Project Status:

    The Cassville Solar Project is an estimated 50-megawatt (MW) solar project located in Grant County, Wisconsin. The Cassville Solar Project will connect into the electrical transmission grid directly through the local substation. Once complete, the project will positively impact the environment and generate enough clean, low-cost energy to power thousands of homes.
    Mashuda Contractors' Work:
    • 1.7 Million CY of Excavation Completed
    • 5.4 Miles of Access Roads Built
    • Grading Activities Completed in 3.25 Months (June 27th, 2022 to October 6th, 2022)
        Click on an image below to open the Cassville Solar Project Photo Gallery.
        Back to Home Page→

        Project Details

        Wautoma Solar Project

        Project Area:

        624 Acres

        Power Output:

        99 Megawatts (MW)

        Estimated Homes Powered:

        25,000

        Location:

        Wautoma, Wisconsin

        Owner:

        Wisconsin Power & Light

        Project Status:

        Expected Completion Q4 2023

        Project Status:

        The Wautoma Solar Project is an estimated 99-megawatt (MW) solar project located in Waushara County, Wisconsin. The Wautoma Solar Project will connect into the electrical transmission grid directly through the local substation. Once complete, the project will positively impact the environment and generate enough clean, low-cost energy to power thousands of homes.
        Mashuda Contractors' Work:
        • 400,000 CY of Excavation Completed
        • 9.7 Miles of Access Roads Built
        • Grading Activities Completed in 2 Months (July 7th, 2022 to August 30th, 2022)
            Click on an image below to open the Wautoma Solar Project Photo Gallery.
            Back to Home Page→

            Project Details

            Beaver Dam Solar Project

            Project Area:

            350 Acres

            Power Output:

            50 Megawatts (MW)

            Estimated Homes Powered:

            13,000

            Location:

            Beaver Dam, Wisconsin

            Owner:

            Wisconsin Power & Light

            Project Status:

            Expected Completion Q4 2023

            Project Status:

            The Beaver Dam Solar Project is an estimated 50-megawatt (MW) solar project located in Dodge County, Wisconsin. The Beaver Dam Solar Project will connect into the electrical transmission grid directly through the local substation. Once complete, the project will positively impact the environment and generate enough clean, low-cost energy to power thousands of homes.
            Mashuda Contractors' Work:
            • 725,000 CY of Excavation Completed
            • 3.4 Miles of Access Roads Built
            • 50% of Grading Activities Completed in 2 Months (September 19th, 2022 to November 11th, 2022)
                Click on an image below to open the Beaver Dam Solar Project Photo Gallery.